Well Shaft Replacement Project

The replacement of the well shaft at the Garfield Ave. pump station began just before the holidays with a crane removing the motor, discharge head, 250 feet of pipe, and the bowl assembly. The results of the inspection were what we assumed they would be for a pump that is 17 years old. The discharge head, 250 feet of pipe and bowl assembly will be replaced with the motor being re-used. The motor is easy to service and was rebuilt only four years ago. The replacement materials should arrive back to MGC in the next few weeks.