Monday, December 5, 2011

Construction Update

The project is moving along on holes 2,4 and 7. All of the drainage and bunker shaping is finished. The liner and sand has been installed on #7 while the crew is working on the second hole today. The new irrigation has been installed on 2 and 4 greens with all new heads to water the greens and new heads to water the rough and bunkers. This is a much more efficient and accurate way to irrigate. The same irrigation set-up was installed on the putting green and #7 a few years ago with great success. We will be laying the sod this week and the fence behind 4 green will be installed early next week. Once the construction is finished I will still have some work to do in-house with the cart path at the 3rd tee and there will be some areas in the rough that will need to be aerified and seeded in the spring.

#7 bunker with sand and liner waiting for sod

Installing the Sand Mat 200 liner

Rolling the irrigation lines after installation